ClickCease

Gaetan Duvaux v Mega Limited [2026] NZERA 182 - redundancy dismissal unjustified on process; pre-selection and withheld scoring; $8,000 compensation plus three months' pay ordered

A senior web developer was made redundant in a large technology department restructure. The ERA accepted the commercial drivers, but found a material process defect: Mega applied the selection criteria before consultation, did not provide the employee's scores, and did not let him meaningfully...


Gaetan Duvaux v Mega Limited [2026] NZERA 182

This is a redundancy case where the Employment Relations Authority (ERA) accepted the employer had genuine commercial reasons to restructure, but still found the dismissal was unjustified because consultation about selection (and how selection was applied) was not done properly. The full determination is embedded at the end of this page.

At a glance

  • Citation: [2026] NZERA 182
  • Registry: Auckland
  • Authority member: Simon Greening
  • Investigation meeting: 23 and 24 February 2026 (Auckland)
  • Submissions received: 23 February 2026 (Respondent) and 26 February 2026 (Applicant)
  • Determination date: 27 March 2026
  • Employee role: Senior web developer (front-end web application)
  • Exit basis: redundancy (position disestablished)
  • Outcome: unjustified dismissal upheld on procedural grounds; no good faith penalty; costs reserved
  • Key orders: $8,000 compensation and reimbursement equal to three months' ordinary time remuneration

Background

Mr Duvaux worked for Mega Limited as a senior web developer from 14 June 2023 until 22 November 2024. Mega operated a cloud storage platform with a large technology department (over 180 staff during the period in question). Mr Duvaux worked in a Webclient team focused on the front-end of Mega's web application.

Mega's evidence was that commercial performance had deteriorated, including a substantial decline in revenue-per-employee. In August 2024 the board commenced a review across the business to identify cost savings and operational efficiencies. That review led to a restructure proposal affecting the technology department.

The restructure process and consultation timeline

  • 4 November 2024: the Chief Technology Officer met with affected employees, provided the restructure proposal, and circulated it by email.
  • 11 November 2024: Mr Duvaux provided written feedback.
  • 13 November 2024: original feedback deadline (later extended).
  • 18 November 2024: extended deadline; Mr Duvaux met with the CTO to discuss the proposal; Mega then communicated its decisions and responses to feedback later that day.
  • 19 November 2024: Mega confirmed in writing that Mr Duvaux's position would be disestablished and employment would end by redundancy.
  • 22 November 2024: the employment ended. Mega paid contractual notice in lieu, statutory/contractual entitlements, and a discretionary additional payment ($5,055.60).
  • 30 January 2025: Mr Duvaux raised a Personal Grievance (PG) alleging unjustified dismissal and seeking remedies.

Mega decided to disestablish 22 roles in the technology department. Mr Duvaux's role was among those disestablished. The critical legal question was not whether Mega could restructure. It was whether the consultation (including selection) met the good faith and fairness requirements in redundancy law.

What the case turned on: selection criteria and meaningful consultation

The ERA's key focus was the way Mega approached selection. The proposal referred to selection criteria, quantified values and weightings. But the Authority found Mega had already applied the selection criteria before the proposal was issued and used that pre-application to determine which roles were likely to be disestablished.

That created a structural problem for consultation: if selection has effectively occurred before employees receive the proposal, the consultation about selection can become hollow. The Authority also found Mega did not provide Mr Duvaux with the actual values (scores) applied to his role, which meant he could not meaningfully engage with how the criteria were applied in his case.

Mr Duvaux provided feedback about the selection criteria and its application, but the Authority found Mega did not specifically address his feedback on the way the criteria applied to his position. Taken together, the Authority treated this as a material consultation defect, not a minor technicality.

Unjustified dismissal in a redundancy context

Redundancy is not automatically unjustified just because process is imperfect. The law draws a line between minor defects and defects that cause unfairness. Here, the Authority found the defect was not minor and resulted in unfair treatment.

Mega submitted that even if the process around selection criteria was improved (for example, by running a fully contestable selection process), the outcome would likely have been the same based on Mr Duvaux's overall scoring. The Authority did not accept that inevitability argument. It found the process defect mattered because, with proper consultation and disclosure of scores, it was possible Mr Duvaux would have had a fair opportunity to influence the scoring outcome and might not have been dismissed.

The Authority also addressed the argument sometimes raised in redundancy cases: that a procedural defect should only produce an unjustified disadvantage finding, not unjustified dismissal. The Authority relied on Employment Court authority confirming that non-minor procedural defects that cause unfairness can support an unjustified dismissal finding in a redundancy setting.

Redeployment

Redeployment was explored. The Authority accepted Mega's evidence that only one potentially available redeployment role existed. It also accepted Mr Duvaux's evidence that the role was not suitable for him. Redeployment was not the deciding factor in the unjustified dismissal outcome.

Remedies

Compensation

The Authority assessed compensation as a non-punitive remedy focused on emotional harm. It accepted the dismissal caused significant stress and financial pressure (including the timing close to Christmas and related family circumstances). At the same time, it noted Mega did consult on the proposal generally and the employment did not end abruptly without any engagement. Taking the impact evidence and the nature of the breach together, the Authority fixed compensation at $8,000.

Reimbursement of lost wages

For lost wages, the Authority applied a key principle in procedurally-driven unjustified dismissal findings: the remedy should reflect the likelihood that employment may still have ended even if a proper process had been followed.

Mr Duvaux sought the equivalent of 10 months' salary, but the Authority limited reimbursement to a three-month period. It accepted Mr Duvaux took reasonable steps to find work after dismissal and was entitled to recover losses for the three-month period following termination. It did not exercise the discretion to award more than three months.

Orders

  • Compensation: Mega must pay Mr Duvaux $8,000 under s 123(1)(c)(i), within 28 days.
  • Reimbursement: Mega must pay a sum equivalent to three months' ordinary time remuneration, within 28 days.
  • Contribution: no reduction for contribution (s 124).
  • Good faith penalty claim: declined (no breach of s 4 found).
  • Costs: reserved.

Practical takeaways

  • Selection must be consultable: if criteria are applied before consultation and scores are withheld, consultation can be found inadequate.
  • Provide scoring detail: if a process uses quantified values/weightings, affected employees will often need their scores to test accuracy and meaningfully respond.
  • Unjustified dismissal can still arise in redundancy: material procedural defects that cause unfairness are capable of grounding an unjustified dismissal finding.
  • Remedy moderation: where the defect is procedural, reimbursement may be moderated to reflect the chance the job would have ended even with a correct process.
If you are considering raising a Personal Grievance (PG), the 90 day notification time limit can be critical.

Read the full ERA determination (embedded)

If the embedded PDF does not load on your device, use the button below to open it in a new tab.

Mobile / tablet tip: Some browsers do not display embedded PDFs reliably. Use the Open button above.


Source: Employment Relations Authority determination hosted on determinations.era.govt.nz.

0800 WIN KIWI

Search
Search articles and guides.
Tip: press / to search

Related articles

Browse all articles
Based on: Unfair Dismissal Cases, Redundancy
Rachel Hankins v Huhtamaki Henderson Limited [2026] NZERA 379 - valid fixed term but unjustified early termination

Rachel Hankins was engaged as an accountant on a fixed term maternity-cover agreement due to end on 15 August 2025. The ERA found the fixed term complied with section 66 of the Employment Relations Act 2000, but Huhtamaki Henderson Limited prematurely ended the employment relationship by requiring the return of company property, cutting off IT access, and treating her engagement as concluded before the agreed end date. The Authority found unjustified dismissal and unjustified disadvantage, ordering $11,500 compensation and four weeks' salary.

ZZP v Commissioner of Inland Revenue [2026] NZERA 367 - medical incapacity dismissal unjustified because final concerns were not put to the employee

ZZP was dismissed by the Commissioner of Inland Revenue on medical grounds after a lengthy absence and a failed return-to-work attempt. The ERA accepted that IRD had given ZZP a reasonable opportunity to recover and had been entitled to treat the medical evidence cautiously. However, the dismissal was unjustified because the decision maker relied on several concerns in the final decision letter that had not been put to ZZP for comment. Reinstatement and lost wages were declined, but compensation was assessed at $25,000 and reduced by 25 percent for contribution, resulting in $18,750 payable.

Jeanette Go v Point Limited [2026] NZERA 369 - genuine redundancy but flawed consultation and undisclosed selection criteria

Jeanette Go was made redundant from her estimator role at Point Limited after a downturn in estimation work. Point accepted its redundancy process was flawed because it did not disclose the selection criteria and did not interview the other estimators. The ERA accepted there was a genuine business reason and that the outcome was unlikely to have changed, but found Ms Go was unjustifiably dismissed and disadvantaged by the flawed process. Point was ordered to pay $18,000 compensation and $5,769.23 gross lost wages. Penalties were declined and costs were reserved.

Selwyn McDonald v Traffica Roading Services Limited [2026] NZERA 360 - on-the-spot dismissal after heated worksite exchange

Selwyn McDonald was summarily dismissed on site by Traffica Roading Services Limited after a heated exchange with director Bashir Ahmed. The ERA accepted Traffica's account that Mr McDonald made serious disrespectful comments with racial connotations, but still found the dismissal unjustified because he was dismissed on the spot without a fair opportunity to respond. Remedies were reduced by 40 percent for contribution. Traffica was ordered to pay $9,000 compensation and $3,800 gross lost wages.

Nata Venceslau Dos Santos v Nresh Group Limited [2026] NZERA 363 - hostile workplace, visa pressure, unjustified dismissal, wage arrears and penalties

Nata Venceslau Dos Santos, a painter's assistant employed by Nresh Group Limited, succeeded in personal grievance claims for unjustified disadvantage and unjustified dismissal. The ERA found Nresh created a hostile and insecure work environment, failed to follow a fair dismissal process, and had no substantive justification for dismissal. Nresh was ordered to pay $25,000 compensation, $1,440 gross lost wages, $2,698.15 gross wage arrears, public holiday entitlements for Good Friday and ANZAC Day 2024, interest, and penalties split between Mr Dos Santos and the Crown.

Browse topics